Radnor commissioners have introduced a working draft of data-center zoning rules addressing power demand, noise, cooling and effects on nearby properties.
The board voted 6–0 to introduce Ordinance 2026-24 on Oct. 26, according to the approved meeting minutes. That vote advanced a draft for further review; it did not adopt the final ordinance.
Zoning Officer Megan Donovin presented the proposal. It would define data centers and allow them as a conditional use in the township’s PLO zoning district, with operating and infrastructure requirements.
The discussion called for a revised draft to return to the township and Delaware County planning commissions. Commissioners also discussed possible input from the Environmental Advisory Council and Board of Health.
The draft included in the meeting packet would require utility-capacity documentation and plans covering energy demand and standby power. It also addresses thermal impacts, emergency generators and eventual decommissioning.
Another provision proposes $100,000 in financial security to address adverse water impacts. The draft would leave operators responsible for remediation costs beyond that amount.
Those provisions describe the proposal reviewed in October. Any revised text and final approval require separate township action.